Did you notice that that plan is a revised plan from this year? Here's the original timeline where all the approvals and processes could have been completed in 2017 -
LeBreton Flats Redevelopment - Timeline | National Capital Commission
Are you seriously suggesting that EM was responsible for all the "approvals and processes", and not the NCC?
His RLG was a bidder, not the entity in charge of the bidding process, and responsible for approvals ...... that's the NCC ..... and they took their own sweet time doing what they do best.
Did you notice (in this timeline) the announcement of
successful proponent was scheduled to happen sometime within a 24 month window of"2017 -2018" ........ and the announcement was made this past January ...... pretty much in the middle of the 24 month scheduled timeline?
There is no date on your timelime, that show anything about when construction would commence..the time line show that the City of Ottawa municipal approval process would happen between 2017 and 2019 .............no mention of construction being started ........ so I guess, after 2019?
I know you're desperately trying to spin things into EM stalled the entire process, and the Arena should already be built by now.......... but that's a Fail my freind.
The Bidding process, was all controlled by the NCC, and any changes to their timelines are on them, not the bidders.
I don't know about you, but I tend to go with the mose recent updated timelines, as they are subject to change.
And right now, according to the most recent NCC timeline
Land conveyance (Phase 1) / Initiation of construction is scheduled to commence in 2019-2020 ........
After City of Ottawa municipal approval process that was (in your timeline) scheduled between
2017-2019 and more recently is scheduled to be completed in
2018-2019.........
the same (end) as the timeline you supplied .........